Work in progress:
Completed AHU #3 duct tie-in to AHU #2.
Air handler unit #3 has been permanently shutdown.
Start layout for tele/data ductbanks.
Starting motor control center (MCC) and swithgear duct bank.
Started mass excavation - currently 95% complete.
Work in progress:
Site shoring around the building is complete - contractor is demobilizing.
130 Piles are complete on the north end of the site (approximately to column line 7).
Temporary ramp into excavation is complete.
Sanitary tie-in on the north side has been…
Image

On February 2, Â鶹ӰԺ State students in the College of Arts and Sciences Learning Community were given a unique opportunity to hear a former United States Ambassador speak on foreign policy issues and U.S.-Russian relations. Steven Pifer, who formerly served as the U.S. Ambassador…
Work in Progress:
Continuing the installation of the temporary duct and assembly of new AHU1 in the East side mechanical room.
Stripped topsoil from addition footprint.
Phoenix air valve replacement in the Annex research labs continues per schedule.
Continue …
Work in Progress:
Floor electrical boxes in room 101 & 104 are complete.
Plumbing under slab is complete in 101 & 104.
The sanitary tie-in and under slab rough-in is complete and inspected for the new restrooms in addition.
Electrical raceways have been …
Work in progress:
Air handler assembly of unit 1 continues in 3rd floor mechanical room east with Roth and Air Enterprises.
Abatement coordination and containment underway in the 3rd floor mechanical room west to prepare to demolish AHU #3 serving the vivarium.…
Work in progress:
Demolition of south stairs is complete including the foundations.
Test pile will be tested on 1/29/16.
Steam Condensate receiver in Williams Hall will take place on Saturday with UFM shutdown.
Auger Cast pile installation to begin next week and progress…
Work in progress:
Electric rough-in is in progress in rooms 101 and 104.