Â鶹ӰԺ

2/4- Smith Hall Renovation Updates

Work in Progress:

  • Floor electrical boxes in room 101 & 104 are complete.
  • Plumbing under slab is complete in 101 & 104.
  • The sanitary tie-in and under slab rough-in is complete and inspected for the new restrooms in addition.
  • Electrical raceways have been installed in crawlspace.
  • Completed miscellaneous demolition the 2nd floor. 
  • Abatement work is substantially complete in the building.

Looking ahead:

  • CMU walls to begin student machine shop & receiving on 2/5.
  • Complete demolition on the second floor.
  • Electrical rough-in will continue on the 1st and 2nd floors.
  • Demolition of the exterior wall and windows at addition location.  This will take place after the slab on grade is poured for the addition (likely 2/8).
  • Mobilization of general trades contractor and begin layout and rough-in on the first floor.

 

POSTED: Monday, February 8, 2016 09:30 AM
Updated: Saturday, December 3, 2022 01:02 AM