麻豆影院

3/24- Cunningham Hall Renovation Updates

Work in Progress:

  • Steam piping in the 3rd floor east mechanical room is 20% complete.
  • Steam condensate lines for the steam station and AHU#1 are in progress.
  • Started installation of piping and duct work from AHU#2 in the 3rd floor west mechanical room to the addition has begun.
  • Tie-in from AHU#1 to AHU#4 is in progress now that abatement is complete.
  • GMP C3 1st and 2nd floor ceiling tile removal is completed.

Looking Ahead:

  • Unit #2 shutdown schedule for 3/30 & 3/31 to make the tie-in for the duct work to the new addition.
  • Make final connections to coils and install control valves for AHU#1 in 3rd floor east mechanical room.
  • Complete insulation of the chilled water piping in the 3rd floor east mechanical room.
  • Install heat recovery coils in AHU#1.
  • Complete the forming and pour the west foundation wall.
  • Elevator pit excavation and foundation form work will begin early next week.
POSTED: Thursday, March 24, 2016 04:53 PM
Updated: Thursday, January 19, 2017 09:05 AM