麻豆影院

2/18- Cunningham Hall Updates

Work in progress:

  • Currently removing the louver on the 3rd floor west mechanical room.
  • Continuing the chilled water piping in the 3rd floor east mechanical room.
  • Started the demolition of AHU#3 in the 3rd floor west mechanical room.
  • Electrician has started ductbank for MCC and switchgear.
  • Phoenix air valve replacement in the Annex research labs continues per schedule. (20 labs completed)

Looking ahead:

  • Starting containment for abatement of AHU#1 in the 3rd floor east mechanical room.
  • Concrete contractor is mobilizing and will be taking delivery of rebar.
  • Continue Phoenix air valve replacement in the Annex. (13 labs to complete)
  • Start forming the elevator pit.
  • Continue chilled water piping in the 3rd floor east mechanical room.
  • Start steam pressure reducing station in the 3rd floor east mechanical room.
  • Continue demolition of AHU#3 in the 3rd floor west mechanical room.
  • Start coordination of duct tie-in between AHU#1 and AHU#4.
POSTED: Thursday, February 18, 2016 12:00 AM
Updated: Saturday, December 3, 2022 01:02 AM